On the particular job we started right in the beginning by obtaining the bespoke environment agency permit through paper work and phone calls, this was obtained in a timely fashion. Once the permit had been obtained we then proceeded to order the 300pe treatment plant from marsh, and once date was confirmed we started the works.
The excavation was done well, we then concreted the base ready for tank delivery. Once the tank had been placed we then encased the tank with more concrete than we care to remember, connected the inlet and outlet, and fired up the kiosk.
The job was carried out in the correct time and on this occasion with a few tweaks we came in under budget. |